Bloomingdale Elementary

Timeline: **

  • Roof - 2013
  • Major Projects - 2014-2015

$4,836,337 *

44,816 square feet

310 students

1300 Orchard Street

Pre-Kindergarten-5th grade

Built 1964

Site is 2 acres


Infrastructure $1,927,088 $43/sf
Replace the heating and cooling system
Replace windows and window systems
Restore the masonry
  Professional services fees $529,948  
  Contingency $192,709  
Roof catch-up PDF $461,175  

Access and Safety $268,896 $6/sf
ADA accessibility, 504 compliance
Bring up to current code; stairs, stairwells and handrails
  Professional services fees $73,947  
  Contingency $26,890  

Classroom Infrastructure - as needed $985,952 $22/sf
Replace flooring
Replace ceilings and lights in classrooms
Replace chalkboards with dry erase boards
Replace storage casework
Replace classroom doors
Replace Venetian blinds
Re-paint classrooms and corridors
  Professional services fees $271,137  
  Contingency $98,595  
  $4,836,337 *  

* All costs are estimates. These figures will be updated when actual costs are available

** Timeline is subject to change