Weisser Park Elementary

Timeline: **

  • Major Projects - 2015-2016

$7,007,554 *

79,014 square feet

544 students

902 Colerick Street

1st through 5th grade

Built 1964

Site is 4.2 acres


Infrastructure $2,884,011 $37/sf
Replace the heating and cooling system
Restore the masonry
  Professional services fees $793,103  
  Contingency $288,401  

Access and Safety $474,084 $6/sf
ADA accessibility, 504 compliance,
Replace fire alarm system
Bring up to current code; stairs, stairwells, and handrails
  Professional services fees $130,373  
  Contingency $47,408  

Classroom Infrastructure - as needed $1,738,308 $22/sf
Replace flooring
Replace ceilings and lights in classrooms
Replace chalkboards with dry erase boards
Replace storage casework
Replace classroom doors
Replace Venetian blinds
Re-paint classrooms and corridors
  Professional services fees $478,035  
  Contingency $173,831  
  $7,007,554 *  

* All costs are estimates. These figures will be updated when actual costs are available

** Timeline is subject to change