Weisser Park Elementary
Timeline: **
$7,007,554 *
79,014 square feet
544 students
902 Colerick Street
1st through 5th grade
Built 1964
Site is 4.2 acres
| Infrastructure | $2,884,011 | $37/sf | |||
| Replace the heating and cooling system Restore the masonry |
|||||
| Professional services fees | $793,103 | ||||
| Contingency | $288,401 | ||||
| Access and Safety | $474,084 | $6/sf | |||
| ADA accessibility, 504 compliance, Replace fire alarm system Bring up to current code; stairs, stairwells, and handrails |
|||||
| Professional services fees | $130,373 | ||||
| Contingency | $47,408 | ||||
| Classroom Infrastructure - as needed | $1,738,308 | $22/sf | |||
| Replace flooring Replace ceilings and lights in classrooms Replace chalkboards with dry erase boards Replace storage casework Replace classroom doors Replace Venetian blinds Re-paint classrooms and corridors |
|||||
| Professional services fees | $478,035 | ||||
| Contingency | $173,831 | ||||
| $7,007,554 * | |||||