Croninger Elementary

Timeline: **

  • Site Improvements - 2013
  • Roof - 2014
  • Major Projects - 2015-2016

$5,717,751 *

54,547 square feet

598 students

6700 Trier Road

Kindergarten-5th grade

Built 1966

Site is 14.6 acres


Infrastructure $2,518,248 $46/sf
Replace the heating and cooling system
Replace windows and window systems
Restore the masonry
Additional parking and parent pick-up lane
  Professional services fees $692,519  
  Contingency $251,825  
Roof Catch-Up $155,100  

Access and Safety $327,282 6$/sf

ADA accessibility, 504 compliance
Replace fire alarm system
  Professional services fees 90,003  
  Contingency 32,728  

Classroom Infrastructure - as needed 1,200,034 $22/sf

Replace flooring
Replace ceilings and lights in classrooms
Replace chalkboards with dry erase boards
Replace storage casework
Replace classroom doors
Replace Venetian blinds
Re-paint classrooms and corridors
Site ImprovementsPDF
  Professional services fees 330,009  
  Contingency 120,003  
  $5,717,751 *  

* All costs are estimates. These figures will be updated when actual costs are available

** Timeline is subject to change