Repair FWCS Information Overview
Back to Repair FWCS
Croninger Elementary
Timeline: **
$5,717,751 *
54,547 square feet
598 students
6700 Trier Road
Kindergarten-5th grade
Built 1966
Site is 14.6 acres
| Infrastructure | $2,518,248 | $46/sf | |||
| Replace the heating and cooling system Replace windows and window systems Restore the masonry Additional parking and parent pick-up lane |
|||||
| Professional services fees | $692,519 | ||||
| Contingency | $251,825 | ||||
| Roof Catch-Up | $155,100 | ||||
| Access and Safety | $327,282 | 6$/sf | |||
ADA accessibility, 504 compliance Replace fire alarm system |
|||||
| Professional services fees | 90,003 | ||||
| Contingency | 32,728 | ||||
| Classroom Infrastructure - as needed | 1,200,034 | $22/sf | |||
Replace flooring Replace ceilings and lights in classrooms Replace chalkboards with dry erase boards Replace storage casework Replace classroom doors Replace Venetian blinds Re-paint classrooms and corridors Site Improvements |
|||||
| Professional services fees | 330,009 | ||||
| Contingency | 120,003 | ||||
| $5,717,751 * | |||||