Repair FWCS Information Overview
Back to Repair FWCS
Irwin Elementary
Timeline: **
$4,209,466 *
40,020 square feet
307 students
3501 South Anthony Blvd.
Kindergarten-5th grade
Built 1927
Site is 4.5 acres
| Infrastructure | $1,940,870 | $48/sf | |||
| Replace the heating and cooling system Replace windows and window systems Restore the masonry Additional parking and parent pick-up lane |
|||||
| Professional services fees | $533,739 | ||||
| Contingency | $194,087 | ||||
| Access and Safety | $240,120 | $6/sf | |||
| ADA accessibility, 504 compliance Bring up to current code; stairs, stairwells, and handrails |
|||||
| Professional services fees | $66,033 | ||||
| Contingency | $24,012 | ||||
| Classroom Infrastructure - as needed | $880,440 | $22/sf | |||
| Replace flooring Replace ceilings and lights in classrooms Replace chalkboards with dry erase boards Replace storage casework Replace classroom doors Replace Venetian blinds Re-paint classrooms and corridors |
|||||
| Professional services fees | $242,121 | ||||
| Contingency | $88,044 | ||||
| $4,209,466 * | |||||