Repair FWCS Information Overview
Back to Repair FWCS
Jefferson Middle School
Timeline: **
$7,649,538 *
85,460 square feet
748 students
5303 Whelock Road
Grade 6-8
Built 1967
Site is 25.7 acres
| Infrastructure | $3,162,020 | $37/sf | |||
| Replace the heating and cooling system Restore the masonry |
|||||
| Professional services fees | $869,556 | ||||
| Contingency | $316,202 | ||||
| Roof catch-up |
$11,550 | ||||
| Access and Safety | $512,760 | $6/sf | |||
| ADA accessibility, 504 compliance Replace fire alarm system Bring up to current code; stairs, stairwells, and handrails |
|||||
| Professional services fees | $141,009 | ||||
| Contingency | $51,276 | ||||
| Classroom Infrastructure - as needed | $1,880,120 | $22/sf | |||
| Replace flooring Replace ceilings and lights in classrooms Replace chalkboards with dry erase boards Replace storage casework Replace classroom doors Replace Venetian blinds Re-paint classrooms and corridors |
|||||
| Professional services fees | $517,033 | ||||
| Contingency | $188,012 | ||||
| $7,649,538 * | |||||