Repair FWCS Information Overview

Repair FWCS Repair FWCS Thank You

Back to Repair FWCS
Jefferson Middle School

Timeline: **

  • Major Projects - 2015-2016
  • Roof - 2013

$7,649,538 *

85,460 square feet

748 students

5303 Whelock Road

Grade 6-8

Built 1967

Site is 25.7 acres


Infrastructure $3,162,020 $37/sf
Replace the heating and cooling system
Restore the masonry
  Professional services fees $869,556  
  Contingency $316,202  
Roof catch-upPDF $11,550  

Access and Safety $512,760 $6/sf
ADA accessibility, 504 compliance
Replace fire alarm system
Bring up to current code; stairs, stairwells, and handrails
  Professional services fees $141,009  
  Contingency $51,276  

Classroom Infrastructure - as needed $1,880,120 $22/sf
Replace flooring
Replace ceilings and lights in classrooms
Replace chalkboards with dry erase boards
Replace storage casework
Replace classroom doors
Replace Venetian blinds
Re-paint classrooms and corridors
  Professional services fees $517,033  
  Contingency $188,012  
  $7,649,538 *  

* All costs are estimates. These figures will be updated when actual costs are available

** Timeline is subject to change